07 apr

AMS-IX connection maintenance

Startdate: April 20th 2010 07:00:00(CEST)
Enddate: April 20th 2010 08:00:00(CEST)

Dear Customer,

Due to our increasing traffic we have recently ordered two additional connections from our Cisco CRS-1 router at Evoswitch to the AMS-IX at the Nikhef datacenter in Amsterdam. Unfortunately AMS-IX switch we are connected to has no more free ports and all our AMS-IX ports at Nikhef have to be migrated to a new bigger switch.
The maintenance will affect one of two connections we have to AMS-IX, so no impact is expected as our whole AMS-IX traffic will be rerouted to our Cisco CRS-1 router at Telecity 2. The expected downtime for our AMS-IX connection at Evoswitch is about 20 minutes within the maintenance window.

The timezone is CEST (UTC+2).

Kind regards,
Leaseweb NOC