14 apr

AMS-IX connection maintenance

Startdate: April 22nd 2010 07:00:00(CEST)
Enddate: April 22nd 2010 08:00:00(CEST)

Dear Customer,

During this maintenance we will migrate to a bigger chassis the second side of the DWDM system which we use to connect our Cisco CRS-1 router at Evoswitch to AMS-IX.
This is one of two connections we have to AMS-IX, so no impact is expected as our whole AMS-IX traffic will be rerouted to our second Cisco CRS-1 router at Telecity 2. The expected downtime for our AMS-IX connection at Evoswitch is about 20 minutes within the maintenance window.
This is the last of three needed maintenances. After this one we will be able to finally increase our AMS-IX capacity from 120 Gbps to 140 Gbps.

Kind regards,
Leaseweb NOC