BBned – Verhuizing van DSL apparatuur

BBned meldt dat zij een verhuizing ingepland hebben voor de in Telecity ondergebrachte apparatuur. BIT neemt haar DSL diensten af in Telecity, en wij zullen dus gedurende dit onderhoud niet of verminderd van de BBned diensten gebruik kunnen maken.

BBned schrijft:

Activity description : Internal move of bbned Telecity node
Affected services : All DSL services of MDF locations connected to Telecity (see attachment) or handed off at Telecity will be interrupted.

Impact : No connection during maintenance. No RADIUS authentication possible for all MDF locations.
Reason : Lack of space to expand in the current room
Short description : build out equipment in room P and rebuild in room Q

De planning van BBned:
0:00-0:20 bring down backbone equipment
0:20-2:00 build out equipment from room P, rebuild in room Q and reconnect fibers
2:00-2:30 checks at equipment level
2:30-4:00 checks at link level, order: backbone ATM switches, routers and voice hand off, ISP hand off links and MDF locations
4:00-6:00 final check of all links and possible spare time for resolving issues

storingsoverzicht-logo
Privacyoverzicht

Deze site maakt gebruik van cookies, zodat wij je de best mogelijke gebruikerservaring kunnen bieden. Cookie-informatie wordt opgeslagen in je browser en voert functies uit zoals het herkennen wanneer je terugkeert naar onze site en helpt ons team om te begrijpen welke delen van de site je het meest interessant en nuttig vindt.