01 jun

Maintenance UPS feed B

Maintenance will be caried out on UPS “B” in our datacenter in Amsterdam. UPS “B” will first be set in internal bypass and than switched in hard bypass. After this the UPS can be powered down to carry out the maintenance. PDU “B” will now be fed from the mains and have no battery backup. Works will start at 08:00 and will be finished around 17:00

01 jun

Maintenance UPS feed A

Maintenance will be caried out on UPS “A” in our datacenter in Amsterdam. UPS “A” will first be set in internal bypass and than switched in hard bypass. After this the UPS can be powered down to carry out the maintenance. PDU “A” will now be fed from the mains and have no battery backup. Works will start at 08:00 and will be finished around 17:00

01 jun

High volume router upgrade

Startdate: June 8th 2011 06:00:00(CEST)
Enddate: June 8th 2011 07:00:00(CEST)

Dear customer,



We are going to upgrade the software on one of our high volume routers at Evoswitch in Haarlem. The maintenance will take place between 6:00 and 7:00 CEST (UTC+2) on the 8th of June 2011. You may see up to 15-20 minutes downtime.



The affected IP ranges:

62.212.82.0/23

62.212.85.0/24

82.192.84.0/24

82.192.94.0/23

83.149.70.0/23

83.149.124.0/22

85.17.24.0/21

95.211.136.0/21

212.7.212.0/23

2001:1AF8:4000::/40





Kind regards,



Leaseweb NOC