Core router upgrade [postponed] [Update]
Startdate: January 26th 2010 00:01:00(CEST)
Enddate: January 26th 2010 01:00:00(CEST)
Dear Customer,
During this maintenance window we will upgrade the core router at Evoswitch.
We will add interface modules.
After the upgrade we will have 16 extra 10GE ports available.
There is no impact expected.
The router supports O.I.R. (online insertion and removal)
Kind regards,
LeaseWeb NOC
[UPDATE]
I’m sorry to report I made a mistake when entering the maintenance date.
The correct date is the eighth of December 2009.
[UPDATE]
We’ve received notification from our distributor.
Delivery of the new modules has been postponed.
As such we have moved this maintenance window forward aswell.