[NL, AMS-01, AMS-11, AMS-12] Power disturbance datacenter facilities

Time: March 27, 2015 09:20:00 (CET)
Dear LeaseWeb customer,

Today, 9:20 CET an external utility power disturbance initiated backup power start up in our AMS-01, AMS-11, AMS-12 datacenter facility. Customer loads have been transferred from utility power to diesel back up.

LeaseWeb engineers are proactively scanning any exceptional situation in our services. Due to this event you might experience longer response times from our Support desk.

Due to this power outage, we are also experiencing issues with our external phone system. As a result of that, the connection to LeaseWeb's phone numbers might not be correctly established.

Next update will be when a significant change to the situation occurs.